TSB Bank · 2015–2018

Fitting the Plan to the Date

Sabadell picked a Sunday for TSB's big IT switch before it knew what TSB needed. When the switch finally came, TSB admitted that half its customers could not bank online.

◷ 3 min read

On the evening of Sunday 22 April 2018, a TSB customer in Hertfordshire opened the bank’s app to see how much he had spent at the pub the night before. His own accounts were there. So were three that belonged to a stranger: a £35,000 savings account, an £11,000 ISA and a business account.

TSB said that glitch lasted about 20 minutes. The rest lasted months. That weekend the bank had moved its 5.2 million customers off the systems of its former owner, Lloyds, and onto a new platform built by its Spanish owner, Sabadell. By Wednesday, TSB admitted that half its customers could not bank online. Business as usual returned only in December.

TSB’s view throughout, the Financial Conduct Authority later noted, was that it would not migrate until it was ready. A review by the law firm Slaughter and May, commissioned by TSB’s board, found that the date had come first.

In July 2015, the day after its takeover of TSB was declared unconditional, Sabadell had already picked a Sunday for the switch: 5 November 2017. It set that expectation without detailed knowledge of what TSB needed. TSB’s own master plan, nine months in the making, landed on the same Sunday. The reviewers called the timetable “ambitious and unrealistic” and said it set a pattern that stuck: choose the end date, then draw a plan to fit it.

The programme fell behind, and in September 2017 TSB postponed. At the board meeting before the announcement, the chair of the risk committee said she was not convinced the bank could deliver in the first quarter of 2018. TSB announced it anyway, nine days into replanning, before anyone had measured the work left. Two weeks later, a member of the risk team emailed the chief risk officer: “We appear to be repeating the previous approach of setting an end date and then fitting to it.”

The new plan had no contingency. The first quarter came and went, and the switch finally happened on 22 April. Other things gave way. Functional testing only finished because chunks of functionality were pushed past go-live, and the planned regression testing phase never ran. Of the four load tests for the app and internet banking, only app logins passed at the original target of 2,250 a minute. The targets were lowered, to 1,500 logins and 1,000 transactions a minute, and the summary of results did not make the change clear. In the first three days, combined logins ran above 1,500 a minute for almost 12 hours.

The load tests also ran on only one of the bank’s two data centres. TSB’s own analysis later named the way its apps behaved across the two centres as the main cause of what digital customers went through, which a one-centre test could not catch. The chief information officer accepted the supplier’s case for testing on one, and the decision appears in none of the minutes the reviewers saw. Before TSB, the reviewers noted, he had in effect run that supplier. Asked whether the board knew, he said it “was not the kind of decisions that we were sharing with the board.”

The board, meanwhile, was told that around 800 defects would go live. The real number was at least two and a half times that.

Paul Pester, the chief executive, stepped down in September 2018. In December 2022 the FCA and the Prudential Regulation Authority fined TSB £48.65 million. Four months later the PRA fined the former CIO, Carlos Abarca, £81,620. He had told the board the supplier was ready, the regulator found, without making sure TSB had got enough assurance from it.

What this story shows

Iron Triangle (Triple Constraint)The first quarter slipped, and the switch finally came on 22 April. To get there, functionality was pushed past go-live, the planned regression testing phase never ran, and a load-test target was cut from 2,250 to 1,500 logins a minute.Planning FallacySabadell set the end date before it knew TSB's requirements, and after the first delay TSB named a new quarter nine days into replanning, before measuring the work left. The review called the original timetable "ambitious and unrealistic".Directly Responsible Individual (DRI)The CIO, who the reviewers said had in effect run the supplier before joining TSB, accepted its case for load testing on one data centre. The decision appears in none of the minutes the reviewers saw, and the review found it unclear who carried the risk of calls like it. The PRA later fined him personally over how he managed the supplier.Pre-mortemAt the board meeting before TSB announced its new quarter, the risk committee chair said she was not convinced it was achievable. The plan that followed had no contingency on the path to being ready.

Sources

  1. Slaughter and May, TSB Review, An Independent Review Following TSB's Migration onto a New IT Platform in April 2018, October 2019 (published by TSB, November 19, 2019)
  2. Financial Conduct Authority, Final Notice to TSB Bank plc, December 20, 2022
  3. Bank of England, PRA fines the former Chief Information Officer of TSB Bank plc for a breach of the PRA's Senior Manager Conduct Rules, April 2023
  4. BBC News, TSB, How it all went so wrong for the bank, April 27, 2018
  5. BBC News, TSB boss Paul Pester to step down after IT fiasco, September 4, 2018